Tieback is a device capable of transmitting tensile forces applicable to a tough region of the ground through the bulb. The tractive effort applied to the Tieback head is transferred to the bulb through the free section.
The tiebacks can be temporary, with an estimated term of use of less than two years (from their installation) and permanent, with a term of use of more than two years.
The tiebacks are composed of:
• Head: Head: which is the part that supports the whole structure (main components: support plate and wedge-grade anchor block);
• Free section: transfers the traction effort applied on the tieback head to the bulb (anchored stretch). The steel must be isolated from the mixture of cement, silica, water and additives;
• Anchored section: transfers the traction effort from the tieback to the ground. In this stretch, the steel is surrounded by the mixture of cement, silica, water and additives (binder).
Allows excavation of the work in the open air
Before drilling a tieback, we must analyze the following aspects:
• Hole location;
• Leveling ground for positioning the drill;
• Possible interference behind the curtain, as well as removals (or deviations);
• Tightness check of the water supply network for the process;
• Drainage arrangements, collection and removal of water used in the process.
Drilling is performed with a drill, according to the slope and length considered in the project. This process is performed by washing (with water), using a coating.
In the case of rock drilling, an air compressor is required to use a hammer (with bits). At the end of the drilling, the interior must be cleaned to eliminate debris.
After cleaning the hole, the tieback itself is installed and this will be done manually. Such operation will be carried out under the supervision of the person in charge of this activity and the introduction process must be slow and careful, to avoid any damage to the tieback by excessive flexing or friction against the walls of the covering or the hole. In addition, precautions must be taken, such as not damaging the corrosion protection, not moving accessories (valves and spacers) and positioning the head at the correct height of the project.
Immediately after installing the tieback inside the hole, the first injection phase (sheathing) begins, which will consist of filling the hole with cement grout, without causing pressure. This injection phase will start with the introduction of a column of rods with a simple plug, inside the injection tubes of the tieback.
The plug is housed slightly above the deepest tieback valve, and water will circulate to remove any debris through this device. Then the cement grout is injected, until it pours through the hole. After a period of time not exceeding two hours, the inside of the tieback injection tube will be cleaned. By introducing a column through which water will circulate until the complete removal of the cement housed inside the tube.
When a minimum time interval of ten to twelve hours is reached after the sheathing execution, we have the start of the controlled pressure injection phase, also known as primary injection.
According to the Brazilian Standard (NBR 5629), all tiebacks of a work must be submitted to prestressing tests.
For tensioning and crimping of tiebacks, prestressing assemblies with pump and hydraulic drive jack will be used and capable of safely reaching the limit test loads.
The prestressing of the tiebacks will take into account a minimum curing time regarding the last injection phase. To control the deformations, independent references will be installed outside the area of influence of the prestressing.
The tests, their stages and stabilization times, the monitoring of displacements and the presentation of reports and graphs, etc., will be developed observing the requirements of NBR-5629, including the loading stages considered by this Standard (temporary or definitive tieback).
The incorporation of the tieback into the structure can only be carried out definitively after the verification of its good performance through the receiving test.
The incorporation will be made through the final wedging of the wires or cordages properly tensioned, next to the support device of the tieback head. As a result, the load applied by the jack will be definitively transferred to the structure.
See other
services